Automatic 3D Snack Pellet Machinery for Food Processing Plants
USD $48,000 - $68,000 /Set
Min.Order:1 Set
Jinan Darin Machinery Co., Ltd.
3D Snack Pellet Machine
Description
Through the extruder cooking, the snacks can be shaped in many different shapes, like shell,
screw, spiral, square tube, circle tube, and so on. After drying and frying, flavoring with the
flavor powder can get delicious snacks food. Also, by changing the shaping machine we can
produce 3D pellet, waved chips, potato chips, shrimp chips and so on.
Raw materials
New Condition 3d Snacks Production Machine adopts potato starch, corn starch, cassava starch, wheat flour, corn flour etc as raw materials.
Capacity
100-120kg/hr, 250kg/hr.
Certificates
CE & ISO9001 Certified.
Products
By changing the shaping machine, we can produce 3D pellet, waved chips, potato chips, shrimp chips and so on.
Machines material
All the machines are made by food grade stainless steel.
Flow chart
Mixing system---Extrusion system----Cutting system---Drying system---Frying system---Flavoring System --Packing system
Voltage in China: Three phases: 380V/50Hz, Single phase: 220V/50Hz, we can make it according to customers' Local voltage according to different countries.
1. the Tri-D pellet making machine
2. single screw food extrusion technology
3. can produce shell, screw, bugle, flake shapes.
Samples
Technical Parameter
Model | Installed power | Real power | Output | Dimension |
DRD-100 | 90kw | 70kw | 100-120kg/h | 27000x2000x2000mm |
Key equipments
Commissioning & After-sales Service
1. We make accurate factory layout design according to customer’s factory size; if the customer
needed, we could make workshop design with electricity power, water supply, gas power, material
storage, final storages, worker’s restroom, etc.
2. After delivering machines to client’s factory, we start to apply for the Visa to client’s country
immediately; normally the vessel needs 20-60 days to the required port, so we have enough time to
get the Visa. While the machines arrives your factory, our engineers are ready to start for the
commissioning service.
3. 1-2 of our engineers will go to your factory to install and adjust the processing line to realize normal
production at shortest time.
4. Our engineers have responsibility to train and teach the workers how to operate, clean, maintain
and repair all the machines, until the workers could well operate the processing line.
5. It normally costs 7-10 days for the commissioning service, and we supply 1 year guarantee
from the date of completion of commissioning service.
6. The engineer’s round-trip flight tickets, accommodation and daily salary USD 100 are on client’s account.
Delivery