3000T/D cement production plant in Africa
USD $200,000 - $2,500,000 /Set
Min.Order:1 Set
Henan Hongji Mine Machinery Co., Ltd.
300-3000T/D cement production process description.
So far, cement production adopt dry cement kiln process, please kindly see production process as follows:
1) raw material prepare and batching
limestone are crushed to suitable size, fly ash or slag is dried by rotary dryer if moisture is high, then limestone, slag, addtives dosing according to ratio.
2)raw material grinding
mixed raw materials are grinded by raw mill, suitable size can be produced by air classifier, if big production plant, we suggest vertical mill.
3) preheat and clinker production
Preheater can save fuel, use fully wast hot air produced from clinker kiln. highest temperature in the kiln 1300-1450, big production plant need decomposing furnace.
4) cement production
cooled clinker with gypsum and other addtives dosing then go to cement mill, suitable size produced from air classifier are send to cement storage or packing system
5) dust collector system
in the whole line, different dust collectors are used. such as crushing parts, ball mill, clinker kiln.
6) control system
automatic control system can be offered, whole process is watched on the computer.
Welcome you inquiry us, professional suggestion and design will be offered according to raw material features and special required .
Certificate
Customer visit
So far, Hongji machinery had been sold to Russia, Pakistan, Korea, Indonesia, Mexio, Australia, Spain, Ukraine, U.S.A ,South Africa, Arabia and so on.Welcome you visit our company.
workshop
So far, there are advanced process equipment in our workshop, such as rolling machine, welding machine, boring machine, which can ensure the machinery's quality