biomass gasification equipment
Negotiable /Set
Min.Order:1 Set
Shangqiu Haiqi Machinery Equipment Co., Ltd.
Introduction to biomass internal-combustion power generation system
Models & specifications:400KW,800KW,1MW,1.5MW,2MW,etc
Applicable raw matrrials:All the plants and organic wastes
The grain size of raw materials is less than 30mm in general.
The water content of the raw materials is lower than 16% in general.
Nature of fuel gas:scope of calorific #118alue 6000 kilojoule/m3(standard)
Tar content 50mg./m3(standard)
Compositions N2 50-60%
Co2 10-20%
CO 10-18%
H2 3-9%
Ch 2-6%
CnHm 0.5-3%
Other 0.5-3%
Operation data:
Auxiliary fuel:Not necessary
Start time:About 45 minutes for cold start
About 15 miutes for hot start
Operator:According to the project scale:1-2 persons for each shift
Raw material consumption:1.0-2.0kg raw materials for generation of each kilowatt-hour
Power generation cost:Will be influenced by many factors. In most regions of china,the cost for generation of each kilowatt-hour is about RMB0.2 yaun.
Environment protection standara:
Exhaust gas:The tail gas of gas engine shall reach the local industrial standard after treatment
Waste water:The cooling water shall be trated internally for recycled use,and no waste water will be dis-charged.
Waste residue:The solid wastes sahll be treated or reused through harmlessness treatment .No waste residue will be discharged.
Noise:The region with noise>75 db will be reused to decrease noise influence.
Smell:The space with smell will be sealed off with negative pressure,and the smell will not outflow