2016 China High Quality And Best Price Making Machine For Vertical //Horizontal Tank
Negotiable /Set
Min.Order:1 Set
Qingdao Yankang Plastic Machinery Co., Ltd.
Parameters
No | specifications | 3000 Liter | |
Model No. | 3 layers | ||
| PRICE FOB QINGDAO |
| |
| Processing material | HDPE/HMWHDPE | |
1 | Extruders | Screw Diameter (Internal) | 110mm grooved barrel |
|
| Screw Diameter(Middle school) | 110mm grooved barrel |
|
| Screw Diameter (Outer Layer) | 110mm grooved barrel |
|
| Plasticizing Capacity | 550kg/h |
|
| L/D | L/D32:1 |
|
| Gear Box Type | Hard surface |
|
| Extruder Drive Motor (Inner) | 75kw |
|
| Extruder Drive Motor (Middle) | 75kw |
|
| Extruder Drive Motor (Outer ) | 75kw |
|
| Heating Load | 110KW |
|
| Max Screw Speed | 60RPM |
2 | Accumulator Die Head | Accumulator capacity | 180L |
|
| Pusher Cylinder | 650x600mm |
|
| Heating Load | 115KW |
|
| Parison Control Cylinder | 560X40mm |
|
| Die-Core size [ Min / Max] | 300-700MM |
|
| Inverter | Siemens |
|
| Max. parison weight | 80KG |
3 | Moulding Clamping Unit | Max opening between Clamping Plate | 3500mm |
|
| Min opening between Clamping plate | 1000mm |
|
| CLAMPING PLATEN Size | 2100x2200mm |
|
| MAX MOLD SIZE | 1900*2300Mm |
|
| Mould Clamping Force | 2200KN |
|
| Mould Thickness | 1000-2200 |
|
| Clamping Pull Bar | 150mm |
4 | Stretching and Blowing Unit | Spreading stroke | 450-1300mm |
|
| Vertical stroke max. | 350mm |
5 | Electrical Control Panel | Thickness controller | 100 points Moog |
|
| Main Operation Panel | Siemens |
|
| Die Head Control Temperature Control | Siemens |
6 | Hydraulic System | Hydraulic Drive motor (Main) | 45KW |
|
| Hydraulic Drive Motor (Parison Control) | 7.5kw |
|
| Oil Tank Capacity | 1200L |
7 | Gripper | Gripped stroke | 350mm |
|
| Discharge Stroke | 2400mm |
8 | Hopper Loader | Loader | 800kg 3pcs |
|
| Hopper | 50kg 3pcs |
9 | Production rate | Productivity | 5pcs/h |
| of 1000 ltr. | Product Weight | 75-90kg |
10 | Delivery period | 5 months | |
11 | Weight of Machine | 65Ton | |
Size of Machine | [L xW xH ] (M) | 12*4.5*7.2 | |
12 | Total power | 350KW | |
13 | Average power Consumption | 250KW |
DELIVERY TIME
4 months after the down payment;
TRAINNING
The Buyer could dispatch their operators to the Seller's factory for training, including machine operation, maintenance & simple repairs;
Or against the requests of the Buyer, the Seller's technician could train the Buyer's operators in the Buyer's factory in the periods of installing & adjusting;
The training is free of charge;
INSTALLATION & ADJUSTMENT
The Seller could dispatch an engineer against the requests of the Buyer to install and adjust the machines for one week in the Buyer's factory.
The Buyer should make a reservation in advance before delivery of the machines;
The Buyer should pay for the engineer's food & board while installation in buyer's factory.
GUARANTEE
The guarantee time is one and half year after the machines normally works in the Buyer's factory, if only the problem is cause due to quality control or any reason by the Seller. We will supply replaced parts free of charge and our engineers will guide you how to solve the problems.
Any problem caused due to irregular operation or incorrect maintenance by the Buyer won't be listed in guarantee coverage.