Instant Noodle Machine/line/plant
USD $25,000 - $35,000 /Set
Min.Order:1 Set
Jinan Darin Machinery Co., Ltd.
Introduction
Instant Noodle Line has perfect technology, compact structure, original design and stable performance,
is developed on the base of requirements of the world market.
Certificate
CE CERTIFICATE, ISO 9001 CERTIFICATE provided.
Features
Instant Noodle Line realizes high automation, convenient operation, low energy and small floor space,
but assures all working procedures from feeding flour to finished products can be accomplished once.
The investment for this line is only one tenth of that lager size equipment, especially suitable to small-sized or self owned enterprise.
The corrugated instant noodle produced by this line is tenacious, smooth and transparent.
It is very easy to be saturated by water. All the machinery is made of stainless steel 304.
Using the advanced technology for nutrient and instant foodstuff complete lines, the plant is innovative with
advanced structure, excellent performance and reliable quality that provide an ideal choice for the investor
in foodstuff industry.
Technical Parameters
Parameters | Electric Type | Steam Type |
Installed Capacity (kw) | 154kw | 30 |
Steam Pressure (kg/m2) | / | 10 |
Output (pcs/8hr) | 11000 | 11000 |
Dimension (m) | 26 x 0.7 x 1.5 | 26 x 0.7 x 1.5 |
Frying Mode | Electric Heating | Steam Heating |
Commissioning & After-sales Service
1. We make accurate factory layout design according to customer’s factory size; if the customer needed, we could make workshop design with electricity power, water supply, gas power, material storage, final storages, worker’s restroom, etc.
2. After delivering machines to client’s factory, we start to apply for the Visa to client’s country immediately; normally the vessel needs 20-60 days to the required port, so we have enough time to get the Visa. While the machines arrives your factory, our engineers are ready to start for the commissioning service.
3. 1-2 of our engineers will go to your factory to install and adjust the processing line to realize normal production at shortest time.
4. Our engineers have responsibility to train and teach the workers how to operate, clean, maintain and repair all the machines, until the workers could well operate the processing line.
5. It normally costs 10 days for the commissioning service, and we supply 1 year guarantee from the date of completion of commissioning service.
6. The engineer’s round-trip flight tickets, accommodation and daily salary USD 60 are on client’s account.